Working Principle, Safe Operating Procedures, and Troubleshooting of Pressure Testing Pumps
Release Date:
2020-12-11
Working Principle of Pressure Testing Pumps Pressure testing pumps are primarily used as pressurizing equipment for various pressure vessels and equipment—such as chemical containers, pump bodies, valves, and pipelines—during pressure testing. Consequently, their most distinctive feature is their ability to deliver very high discharge pressures; typical pressure testing pumps can reach several hundred atmospheres, while ultra-high-pressure models may exceed ten thousand atmospheres. However, their flow rates are generally quite low, often less than 1 m³/h. Nevertheless, the small output flow does not prolong the testing time, because pressure testing of a vessel does not require the pump to completely fill the container before the test can be considered complete. The usual procedure involves first filling the vessel with liquid, then connecting a fitting to the pump’s outlet. Leveraging the principle that liquids transmit force uniformly, once the pump reaches a certain pressure at its outlet, the same pressure is simultaneously applied inside the vessel, thereby achieving the desired test pressure. The working fluid for pressure testing pumps is typically water, though pure mineral oil may also be used. These pumps are generally available in two main types: manual and electric. Manual pressure testing pumps, due to their high discharge pressure, are usually single-acting reciprocating plunger pumps. They consist mainly of a pump body, plunger, hand crank, and drain valve. Electric pressure testing pumps have a basic structure largely similar to manual models. Their cylinder comprises four single-acting plungers. The transmission mechanism relies on an electric motor driving a worm gear reduction unit, which in turn uses an eccentric cam on the worm wheel shaft to drive the plungers in a reciprocating motion. Safety Operating Procedures for Pressure Testing Pumps 1. Conduct pressure tests strictly in accordance with the specified requirements; test pieces must be clean, tidy, and easy to inspect. 2. Prior to testing, inspect the electrical system and grounding conditions, calibrate the pressure gauge, verify that the pump is operating properly and adequately lubricated, and ensure that the maximum scale of the pressure gauge is at least 1.5 times the test pressure. 3. During pre-test preparations, arrange the positions of the inlet and outlet ports. When filling the vessel with water for testing, first open the vent hole and remove the pressure gauge to allow all air inside the vessel to escape. Once water begins to flow from both the vent hole and the pressure gauge connection, reinstall the gauge and close the vent hole. 4. Increase pressure slowly and never exceed the specified limit; after the test piece has reached the target pressure, striking or hammering is prohibited. If defects are discovered in the test piece or associated piping, reduce the pressure to zero before addressing them; working under pressure is strictly forbidden. 5. For negative-pressure or low-pressure test pieces and small vessels, it is permissible to raise the pressure in one step to the designated level and then hold it for inspection. Larger-volume test pieces, however, should be pressurized and inspected in stages. 6. Test pieces must be placed securely and stably, and the tested areas must pass inspection without any leakage. 7. After completing the pressure test, drain the water and relieve the pressure before removing bolts. In winter, be sure to drain all water immediately after testing to prevent freezing damage to equipment. 8. Tighten bolts evenly to avoid localized deformation that could lead to rupture. 9. Pressure testing pumps must be operated by designated personnel; each test requires at least two people, with a dedicated supervisor on duty until the water has been fully drained. 10. Mark any defects found during inspection and record them in the pressure test log. Common Faults in Pressure Testing Pumps Pressure Does Not Rise or Rises Slowly 1. Loose switch, deformed steel ball, or non-sealing inlet valve. 2. Clogged filter screen or water inlet pipe, or leaks at pipe connections. 3. Leakage at the plunger area. Solutions: 1. Tighten the switch and replace the (3) steel ball, (14) glass ball, or G9Crl3 steel ball. 2. Replace the medium and clear any blockages to eliminate leaks. 3. Replace the YX sealing ring (9). Short Holding Time 1. Minor leakage at the outlet valve. 2. Leaks at other component connections. Solutions: 1. Clean the valve core and replace the sealing ring. 2. Tighten connection bolts and replace seals.
Working Principle of the Pressure Testing Pump
A pressure testing pump is primarily used as a pressurizing device for various pressure vessels and equipment—such as chemical process vessels, pump casings, valves, and pipelines—during pressure testing. Its most distinctive feature is its ability to deliver very high discharge pressures; typical pressure testing pumps can achieve several hundred atmospheres, while ultra-high-pressure models can reach over ten thousand atmospheres. However, their flow rates are generally low, often less than 1 m³/h. Nevertheless, the small output flow does not prolong the duration of the pressure test, because the test is not completed simply by filling the vessel to capacity with the pump. The standard pressure-testing procedure involves first filling the vessel with liquid and then connecting a fitting to the pump’s outlet. Leveraging the principle that liquids transmit pressure uniformly, once the pump’s outlet pressure reaches a specified level, the pressure within the vessel rises accordingly, thereby achieving the desired test pressure.
The working fluid for pressure testing pumps is typically water, though pure mineral oil may also be used. Pressure testing pumps are generally available in two main types: manual and electric.
Manual pressure-testing pumps, owing to their high discharge pressure, are generally single-acting reciprocating plunger pumps. They primarily consist of a pump body, plunger, hand crank, and drain valve, among other components.
The basic structure of an electric pressure-testing pump is broadly similar to that of a manual pressure-testing pump. The pump cylinder consists of four single-acting plungers. The drive mechanism relies on an electric motor that powers a worm-gear reduction unit; an eccentric cam mounted on the worm-gear shaft drives the plungers in reciprocating motion.
Safety Operating Procedures for Pressure Testing Pumps
1. Conduct pressure testing in strict accordance with the specified requirements; test components shall be clean, free of debris, and easy to inspect.
2. Prior to pressure testing, the electrical system and grounding shall be inspected; the pressure gauge shall be calibrated; the operation and lubrication of the pressure-testing pump shall be verified as satisfactory; and the maximum range of the pressure gauge shall be no less than 1.5 times the test pressure.
3. During pre-commissioning for the pressure test, the locations of the water inlet and drain outlet shall be designated. When filling the vessel with water for the pressure test, first open the vent valve and remove the pressure gauge to allow all air inside the vessel to escape. Once water begins to flow from both the vent valve and the pressure gauge connection, reinstall the gauge and close the vent valve.
4. Pressure shall be increased slowly and must not exceed the specified test pressure; striking or hammering is prohibited once the test piece has reached the designated pressure. If defects are detected in the test piece or piping, the pressure must first be reduced to zero before any repairs are made; work under pressure is strictly forbidden.
5. For test pieces and small containers subjected to negative or low pressure, the pressure may be increased in a single step to a specified level, followed by a pressure-holding inspection. For large-volume test pieces, pressure may be increased and inspected in stages.
6. Test-pressure components must be placed securely, and the test-pressure areas must pass inspection without any leakage.
7. After the pressure test is completed, first drain the water and relieve the pressure before removing the bolts. In winter, the water must be drained immediately after the pressure test to prevent equipment damage due to freezing.
8. Bolts shall be tightened to ensure uniform stress distribution, thereby preventing local deformation and subsequent cracking.
9. The pressure-testing pump shall be operated by a designated person; each pressure test must be conducted by at least two personnel, with a dedicated supervisor on duty who remains at his post until the water has been released.
10. Mark the inspected defect locations and complete the pressure test record.
Common Fault Symptoms of Pressure Testing Pumps
Pressure does not rise or rises slowly.
1. The valve is not tightened properly, the steel ball is deformed, and the water inlet valve is not sealed.
2. The filter screen inlet pipe is clogged, or there is a leak at the pipe connection. 3. There is a leak at the plunger assembly.
1. Tighten the switch and replace the (3) steel ball (14) with either a glass ball or a G9Cr13 steel ball.
2. Replace the medium to remove blockages and eliminate leakage.
3. Replace the YX sealing ring (9)
Short holding time
1. Minor leakage from the outlet valve.
2. Leakage at connections of other components.
1. Clean the valve spool and replace the O-rings.
2. Tighten the bolts at the connection points and replace the seals.
Latest News
We need to help you.Provide a solution?
Please contact our professionals.
If you need assistance, please leave your contact information, and we will get in touch with you within 24 hours.
National Sales Hotline: 24/7
Address: No. 1 Xinggang Road, Zhougang Industrial Park, Jiangning District, Nanjing City